The new 15,000-seat arena in Miskolc was developed with a divisible event space, skyboxes, and an under-pitch heating system. With the exception of the roof structure, the stadium’s primary load-bearing components, including the column sockets, columns, portions of the reinforced concrete walls, and floor slabs, were constructed using precast reinforced concrete elements.
The transverse structural frames, consisting of fixed precast columns, inclined beams, and reinforced concrete walls, provide support for the precast stepped grandstand elements. The stadium’s spectator stands were therefore largely realized using precast concrete technology.
The city-side and visitor-side reception buildings located on the northern and southern sides of the stadium, each with nominal dimensions of 8.40 × 54.58 m, are structurally independent from the arena itself. These single-bay buildings were also constructed predominantly from precast reinforced concrete elements.